4P644738-1 – 2021.02
f Smart Grid pulse meter
1 Install the components of the Smart Grid relay kit as follows:
K1A, K2A Relays
X10M Terminal block
a Screws for X10M
b Screws for K1A and K2A
c Sticker to put on the high voltage wires
d Wires between the relays and X5M (AWG22 ORG)
e Wires between the relays and X10M (AWG18 RED)
B
A
B
X5M
5 6 9 10
1 2 3 4
K1A K2A
b b
X10M
a
2 Connect the low voltage wiring as follows:
3 Connect the high voltage wiring as follows: