17 3P362438-3H English
If the piping length between the outdoor units exceeds 6.5 ft. (2 m),
create a rise of 8 in. (200 mm) or more in the suction gas and High/
Low pressure gas line within a length of 6.5 ft. (2 m) from the kit.
If≤6.5ft.(2m)
1
2
a
If>6.5ft.(2m)
1
a a
c
2
b b
c
1 To indoor unit
2 Piping between outdoor units
a 6.5 ft. (2 m)
b 8 in. (200 mm)
c > 6.5 ft. (2 m)
NOTE
There are restrictions on the refrigerant pipe connection order be-
tween outdoor units during installation in case of a multiple outdoor
unit system. Install according to following restrictions. The capacities
of outdoor units A, B and C must fulll the following restriction condi-
tions: A≥B≥C.
A B C
1 2 3
1 To indoor unit
2 Outdoor unit multi connecting
piping kit (rst branch)
3 Outdoor unit multi connecting
piping kit (second branch)
8.2.6. Branching the refrigerant piping
1 For installation of the refrigerant branching kit, refer to the installa-
tion manual delivered with the kit.
A
B
±
3
0
°
1
1
Horizontal
Vertical
1 Horizontal surface
Mount the REFNET joint so that it branches either horizontally or
vertically.
Mount the REFNET header so that it branches horizontally.
2 Installation of the multi connection piping kit.
A
1
B
1
C
D
±15°
C > 4-3/4 in. (120 mm)
D > 19-11/16 in. (500 mm)
Install the joints horizontally, so that the caution label (1) attached to
the joint comes to the top.
- Do not tilt the joint more than 15° (see view A).
- Do not install the joint vertically (see view B).
Make sure that the total length of the piping connected to the joint
is absolute straight for more than 19-11/16 in. (500 mm). Only if a
straight eld piping of more than 4-3/4 in. (120 mm) is connected,
more than 19-11/16 in. (500 mm) of straight section can be ensured.
Improper installation may lead to malfunction of the outdoor unit.
8.3. Guidelines for handling stop valve
8.3.1. Cautions on handling the stop valve
Make sure to keep all stop valves open during operation.
The gure below shows the name of each part required in handling
the stop valve.
The stop valves are factory closed.
When handle the stop valves, be careful not to damage the port
pipes around (refer to P22).
3
4
1
2
1 Service port and service port
cover
2 Stop valve
3 Field piping connection
4 Stop valve cover
345
1 Service port
2 Cap
3 Hexagon hole
4 Shaft
5 Seal
01_EN_3P362438-3H.indb 17 1/14/2015 10:19:40 AM