Zone Holiday Schedule
Start Stop Setting
12/22 01/01 Secondary
07/03 07/05 Secondary
-- -- -- -- ------
-- -- -- -- ------
The holiday schedule allows you to set a span of one or more days to run
the schedule selected: Primary or Secondary. Up to 4 holiday schedules
may be set. While running a holiday schedule, it supersedes the weekday
schedule. If a span of only one day is needed, consider using the special
day scheduler described next.
Start – Choose the day and month to start the holiday. Stop
– Choose the day and month to end the holiday. Setting –
Choose which schedule will run during the holiday.
When the clock reaches the selected start day (at 12:00 midnight) the
schedule that is selected will run. When the clock reaches the selected stop
day (at 12:00 midnight) the holiday schedule will end, and the normal
weekday schedule will take over.
When (------) is shown, no holiday schedule is set.
Zone Spec Day Schedule
This screen will only appear on the Unit #1.
The special day schedule is like the Holiday schedule except it is limited to
just one day that will run the schedule selected: Primary or Secondary.
When a special day schedule is set, it supersedes the weekday schedule.