Operation Overview - 65 JT30 /JT30 All Terrain Operator’s Manual
Planning
CMW
Planning
1. Gather information about jobsite. See page 70.
2. Inspect jobsite. See page 71.
3. Classify jobsite. See page 73.
4. Plan bore path. See page 75.
5. Check supplies and prepare equipment. See page 86.
6. Load equipment. See page 94.
Setting Up at Jobsite
1. Prepare jobsite. See page 85.
2. Mix drilling fluid. page 138
3. Unload drilling unit from trailer. See page 97.
4. Assemble drill string. See page 106.
5. Position drilling unit and drill frame. See page 102.
6. Assemble strike system. See page 132.
7. Anchor drilling unit. See page 130.
8. Connect fluid system. See page 102.
9. Calibrate tracker with beacon that will be installed in beacon housing. See tracker operator’s manual.