3.4 Technical data
Specification
*.42L.42T
*.48L.42T/*.48L.50T
*.51L .50T
Rated capacity of the main lift
4200KG
4200KG/5000KG
5000KG
Applicable wheel track of the main lift
11001800mm
11001800mm
11001800mm
Applicable wheel base of the main lift
4000mm
4600mm
4900mm
Full raised height of the main lift
2060mm
Initial height of the main lift
360mm
Full raised time (with rated load)
50s
Full lowered time (with rated load)
50s
Rated capacity of the wheel free lift
3500KG
Applicable wheel track of the wheel free lift
11001800mm
Applicable wheel base of the wheel free lift
21002800mm
Full raised height of the wheel free lift
450
Hydraulic working pressure ( MPa )
24
24 / 29
29
Pneumatic working pressure (Bar)
6-8
Oil tank volume
18L
INSTALLATION INSTRUCTIONS
4.1 Preparations before installation
4.1.1 Space requirements.
Refer to 3.3 for the dimensions of the lift. There must also be a clearance of at least 1 meter between the lifting platform and fixed
elements (e.g. wall) in all lifting positions. There must be sufficient space at the ends of the lifting platform for driving vehicles on and off.
To stop vehicles colliding with the ceiling, it is advisable to fit an overhead light barrier in low ceiling buildings.
4.1.2 Foundations and connections
The user must have the following work performed before erecting the lift.
Construction of the foundation following consultation with the manufacturer’s customer service or an authorized service agent.
Routing of the wiring to the installation location. The user must provide fuse protection for the connection. Electrical system
connection must be done by licensed technicians. Requirements for power supply cable of the installation site: at least 2.5mm
2
wire core for 3Ph power and 4.0mm
2
wire core for 1Ph power.
Refer also to the corresponding information on the name plate and in the operation instructions. Before doing electrical
connection, make sure the lift is electrically adapt to the local power supply.
4.1.3 Foundations preparations
Please refer to Annex 1 for recessed floor dimensions.