Installation, Operation and Parts Manual
EE-6603BWF
5) Repeat the above levelling steps if synchronization is not achieved.
Level the wheel free lift
1) Turn the selection switch on the control panel to the” wheel free lift” and the selection switch in the control cabinet to
“levelling”mode.
2) Turn on levelling valve for the” wheel free lift” at the hydraulic block in the control unit.
3) Push the "UP” button until both lifting platforms of the jack go utmost top to bleed air in cylinders.
4) Turn off the ball valve.
5) Push DOWN I button till the platform of “wheel free lift” have fully lowered.
PUSH UP BUTTON TO CHECK. THE wheel free lift SHOULD BE SYNCHRONIZED BY THIS STEP.
IF STILL NOT,
Turn on the valve again and push the UP button until both platforms are at same level.
Close the ball valve. Push the UP button to check the synchronization.
4.4 Items to be checked after installation.
Screw torque of expansion bolts : 60-80N•m;
Noise with rated load ≤75db;
Grounding resistance: not bigger than 4Ω;
Height difference of the two platform ≤5mm;
Mechanical locks are robust and synchronized when running with rated load ;
If the control button works as “hold to run”?
If limit switches work well?
If grounding wire is connected?
If the lift rises and lowers smoothly?
If there is no abnormal noise during running with rated load?
If there is no oil leakage when running with rated load?
If there is no air leakage when running with rated load?
If expansion bolts, nuts or circlips are well secured?
If max lifting height is 1700mm (above ground)?
If safety advices, name plate and logos are clear?