Installation Plan and Unpacking
Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual P-164000639—Rev 1 www.eaton.com/powerquality 3-9
2. Use a forklift or pallet jack to move the packaged cabinet to the installation site, or as close as possible,
before unpacking. If possible, move the cabinet using the pallet. Insert the forklift or pallet jack forks
between the supports on the bottom of the pallet. See Figure 3-3 for the IBC–SW cabinet center of gravity
measurements.
Do not tilt the cabinet more than 10° from vertical or the cabinet may tip over.
3. Set the pallet on a firm, level surface, allowing a minimum clearance of 3m (10 ft) on each side for
removing the cabinet from the pallet.
4. Remove the protective packaging material from the cabinet and recycle in a responsible manner. Retain
the parts kit box packed at the top of the cabinet.
5. Inspect the contents for any evidence of physical damage, and compare each item with the Bill of Lading.
If damage has occurred or shortages are evident, contact an Eaton service representative immediately to
determine the extent of the damage and its impact on further installation.
NOTE For the following step, verify that the forklift or pallet jack is rated to handle the
weight of the cabinet (see Table 3-1 for cabinet weight).
NOTE While waiting for installation, protect the unpacked cabinet from moisture, dust, and
other harmful contaminants. Failure to store and protect the EBC properly may void
the warranty.