3 INSTALLING THE SWITCH
SELECTING A SITE
Switch units can be mounted in a standard 19-inch equipment rack or on a flat
surface. Be sure to follow the guidelines below when choosing a location.
The site should:
be at the center of all the devices you want to link and near a power
outlet.
be able to maintain its temperature within 0 to 50 °C (32 to 122 °F)
and its humidity within 10% to 90%, non-condensing
provide adequate space (approximately two inches) on all sides for
proper air flow
be accessible for installing, cabling and maintaining the devices
allow the status LEDs to be clearly visible
Make sure twisted-pair cable is always routed away from power lines,
fluorescent lighting fixtures and other sources of electrical interference,
such as radios and transmitters.
Make sure that the unit is connected to a separate grounded power outlet
that provides 100 to 240 VAC, 50 to 60 Hz, is within 2 m (6.6 feet) of each
device and is powered from an independent circuit breaker. As with any
equipment, using a filter or surge suppressor is recommended.

Table of Contents

Other manuals for Edge-Core ECS4310-26T

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Edge-Core ECS4310-26T and is the answer not in the manual?

Edge-Core ECS4310-26T Specifications

General IconGeneral
BrandEdge-Core
ModelECS4310-26T
CategorySwitch
LanguageEnglish

Related product manuals