12 – INITIAL CHECK
MODEL WIZARD UP30 M
Preliminary
checks
DESCRIPTION YES NO NOTE
1
Availability of use instructions and related electrical and hydraulic
diagrams.
2 Completeness of supply, suitability and compatibility of components.
3 Check flatness of the ground in installation position of the machine.
4
Check minimum safety distances from walls or other machines,
minimum room height.
5 Correct assembly of bolted parts and joints, stability of fixing systems.
6 Presence, suitability and correct operation of the main switch.
7 Eligibility of the power supply line (from the main switch to the lift).
8
Correspondence between the main voltage and that foreseen for the
lift motor.
9
Correct ground connection of the metal structure, of the
electromechanisms / electrical users.
10
Absence of surface defects (painting, burrs, sharp edges, dents,
bends)
11
Control of the stroke spaces of the lift, absence of foreign bodies or
obstacles.
12 Thread tightening check.
13 Cleaning the lift installation area.
14 Maximum oil supply pressure: 260 [bar].
15 Functional test of the machine.
16 Functional test of safety devices.
17
Operation of the lift anti-crushing device (minimum light of 120 mm
between parts which present a risk of crushing)
18 Preservation of manuals.