4. Operation
4.1 Start-up
Warning!
Before activating the unit, the user must make sure that the unit has been
correctly installed and that the connections are properly made.
The supply voltage can then be switched on.
The high voltage generator is switched on via the master switch.
The generator is operational immediately after the supply voltage is
switched on. High voltage applies at the outlet sockets as soon as the
24 V release signal is transmitted.
The pilot lamp ligths up when the high voltage is switched on.
4.2 Use
Select the desired output voltage via the rotary button.
Warning!
High voltage may also be present if the rotary button is turned fully anti-
clockwise to the stop.
Anti-clockwise turn: Reducing the output voltage.
Z00182y
Clockwise turn: Increasing the output voltage.
Z00183y