7.4.6 Commissioning check
This procedure is to confirm that all calibration steps have been completed appropriately.
1. Navigate to: Diagnostics → Device check → Commissioning check → Commissioning
check
2. Select the Start.
Executing is shown on the verify drum table.
3. Select the Start.
4. Confirm that the Commissioning check shows the Finished.
5. Confirm that the Result drum check is passed.
This completes the commissioning check procedure.