Envent Engineering Ltd. Page 23 Revision 2.4
Unpacking the Analyzer
If damage is found in the shipping container see previous section
1. Open the shipping container and remove the foam packing or other packing
materials from the shipping box
2. Take out the analyzer and the start-up kit
The 330S H
2
S analyzer with a standard Sample conditioning system weights
approximately 105 lb. Unpacking and transporting requires a minimum of two
persons.
3. Make sure the start-up kit is complete (refer to list below). For some special and
more complex analyzers, there might be extra parts in the start-up kit.
Standard spare parts for 330S H
2
S analyzers:
1. 330S Customer Binder
• Customer Manual(s) and Addendums
• Factory Calibration Certificate
• Factory Configuration
• Drawing Package
• Cal Gas Certificate(s)
2. USB flash drive (containing all documentation)
3. 300' H
2
S Sensing Tape. Part No. 330133XS
4. 1 Liter Analyzer Fluid. Part No. 330129
5. Funnel
6. 330S Serial Comm. External Cable (USB to Mini USB). Part No. 600002
7. Humidifier (uninstalled). Part No. 330061 (Part No. 330061D for SDS)
8. Bolts For explosion proof enclosure (x22)