1. Validate the setups matches 56X Setup Requirements
2. Perform visual inspections for leaks
3. Load All Defaults
4. Fill barrel with CO
2
until tank pressure reaches to 10 psig, then purge barrel until tank
pressure is at 0 psig. Repeat this process for 3 times to empty out the air.
5. Press the FILL” & “Beater” button to fill barrel. Fill barrel to just below the Relief Vent
Valve. NOTE: In the filling process, motor will need to be stopped to check
filling level, and relief vent valve will be pulled to allow filling
6. Press the OFF, the Defrost then the Run button.
7. Verify and/or update the Time, Date, DL Savings (where applicable), Wake/Sleep Time
and Defrost Times.
8. After freeze down, pour several 12oz cups to check product quality.