START-UP AND CALIBRATION
070002_3_B
FGP 50/2 EVO-2
10
START-UP AND CALIBRATION
BURNER CALIBRATION
PUMP CALIBRATION
ATTENTION: Before starting the burner it is necessary to respect the general norms of security; especially
check:
- Electrical supply
- The tightness of the plant and its correct realization
- The presence of water in the plant
- The ventilation of the boiler location
- The correct function of the thermostats and pressure switches of the boiler.
WARNING
Fig. 10 Pump calibration
LEGEND
1) Delivery 1st stage
2) Delivery 2nd stage
3) Pressure checking
4) Pressure calibration screw
3
4
12