Step 6: Connect gas supply and commission
Gas installation, connection and commissioning must meet the requirements of AS/NZS 5601.1:2013
and be installed and certified by a suitably qualified person.
In order to access the testing area, it is necessary to first remove the front cover.
Remove the front cover by following the Front Cover Removal Process’ in this guide.
Leak test all joints.
GD13 models have a glass failure safety switch at the base of the
opening. The safety switch turns the appliance off if the glass is not in
position. The 3mm pin will need to be held down to complete
commissioning. It is recommended that masking tape is used to hold
the safety pin down.
NOTE: The masking tape must be removed once testing
is completed.
Switch the appliance on.
Test/adjust high first and then the low pressures against
rating plate specifications.
The GD13 has an input of 15-20MJ/h from one gas injector at the pilot side
of the burner tray.
In the unlikely event that the rating plate is not attached, Do Not commission the fire and contact The Fire
Dept. immediately.
Switch the appliance off.
Replace the front cover by following the Front Cover Installation Process’ in this guide.
Switch the appliance on.
Note: due to lack of firebed and glass, it may be necessary to manually light burners.
Switch the appliance off.
Lay firebed in accordance with instructions in Step 7 of this guide.
Send gas certificate to appropriate person.
Safety switch pin
Off position
Burner with vermiculite
(see how to lay vermiculite in this guide)
Burner exposed