01
[]
o
Open and operate vents and vent fans, including the
range hood fan.
Inspect the 120-volt electrical system - power cord,
converter, inverter, all outlets, and any exposed wiring.
If
defects are found, refer service to your dealer or an
authorized Fleetwood Service Center.
Prepare the generator for operation following instruc-
tions in the generator operating manual in your
Owner's Information Package.
Start and run generator. Check the generator exhaust
system for leaks or deterioration.
Operate l20-volt appliances and air conditioners. Be
sure
to
uncover air conditioner shroud(s).
Inspect the
LP gas system and check for leaks
as
described in the
LP
Gas System chapter.
If
the LP tank
shows signs
of
rust or corrosion, have it inspected by a
qualified
LPG technician.
Operate each LP gas appliance. Observe all
burner/pilot flames for proper color and size. In any
case, have the
LP gas regulator adjusted for proper
pressure by a qualified technician.
Inspect and clean the interior.
Check the sealant around all roof and body seams and
windows. Reseal
if
necessmy. See Sealant Renewal
section.
Lubricate all exterior locks, hinges, and latches.
Reinstall windshield wiper blades or remove protective
covers. Check wiper/washer operation.
PACE
ARRow
SroRAqE
/0,//
1=
I
-~

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Fleetwood Pace Arrow 2000 and is the answer not in the manual?

Fleetwood Pace Arrow 2000 Specifications

General IconGeneral
BrandFleetwood
ModelPace Arrow 2000
CategoryMotorhomes
LanguageEnglish

Related product manuals