OPM_SGS_USM_M40_M50_1US_V020.doc Operating Manual SG Series 400 & 500 kVA
7.2.2 Complete UPS shutdown (No Load supply)
NOTE !
The Load must be disconnected.
Initial status:
Load supplied from Inverter.
1. Press total off button.
Load is disconnected from UPS.
Rectifier is shut down and all output and
input contactors will be opened.
LED’s, Rectifier, Inverter and Load are OFF.
Press mute, to reset alarm and buzzer.
The Battery remains connected to the UPS in case of configuration without external
Battery Breaker Release!
2. Open Q1 (Pos. O).
LED service check lights up.
4. Disconnect the Battery from the UPS (only for UPS configuration without external
Battery Breaker Release).
Wait 5 minutes for DC-Link Capacitors to discharge.
Before you proceed with any kind of
intervention on the UPS, make sure the
DC-Link voltage be less than 15 VDC.
Ub=15V
Ib= + 0A
Battery Temp= + 20
°
C
Charge Level= 87%
Autonomy = 12min
metering
alarms
parameters
+
ok
4. Disconnect the Utility.
All LED’s are OFF.
END OF PROCEDURE