2 Responsibilities of the Purchaser/Customer
To ensure that the installation of an Innova System meets the purchaser or customer expectations,
it is important to determine who will take responsibility for the various items during the system
installation process. To help you in determining these responsibilities, review the following
checklists with the customer and assign responsibilities as appropriate:
Tool and Test Equipment (Chapter 7, Section 2, Tools and Test Equipment)
Pre–Installation Checklist (Chapter 7, Section 5, Pre-Installation Checklist)
Contract Changes:
Be sure to inform the customer that the cost of any alteration or modification not specified in the
sales contract are liable to the customer.
The following GE-supplied equipment must be installed by the Hospital's Contractors, per room
drawings:
PDB (Electrical Power Distribution Box or Main Disconnect Panel)
LC Gantry & Table baseplate hole drilling (Per supplied template)
LCD Monitor suspension stationary rails
LC Gantry baseplate grout
LC Gantry baseplate
Omega/Innova
IQ
Table common baseplate (if applicable)
NOTE:
In case of Innova
IQ
Table upgrade, it is critical to have the table baseplate flushed in
the concrete.
Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare Direction 5160944-13-1EN, Revision 2
26 2 Responsibilities of the Purchaser/Customer