1.8 Layout Constraints
The X-Ray tube Chiller elevation cannot exceed 3 meters (9.84 feet) in height.
Minimum distance between Digital Detector and UPS is 3 m (118 inches) (Fluoro
UPS option).
The distance of the Detector chiller cannot exceed 3 m (1 floor) in height below the
detector.
Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare Direction 5160944-13-1EN, Revision 2