Chapter 1 General requirements Page 19
Section 1.3 Customer responsibilities
1.3.1 Contract changes
The cost of any alterations or modifications not specified in the sales contract are the responsibility
of the customer.
1.3.2 Responsibilities of the customer
The customer is responsible for completing pre-installation activities. This includes procuring and
installing all required materials and services to prepare the site for installation. This responsibility
includes providing:
1. A clean and safe work environment for installation of the product (finished floor, ceiling, walls,
and proper lighting).
2. A secure location for storing loose items such as the service keyboard.
3. A location suitable for charging the system and downloading images (Optima XR220amx
only). See Chapter 3 Environmental (HVAC) requirements.
4. Electrical power of the required voltage. See Chapter 4 Electrical requirements.
5. An Ethernet jack as described in Chapter 5 Communication requirements.
6. If the Wireless Option is purchased, the wireless access point and wireless network
requirements described in Chapter 5 Communication requirements.
7. If the tablet holder option is purchased, please check with customers the tablet is ready to
install.

Other manuals for GE Optima XR220amx

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE Optima XR220amx and is the answer not in the manual?

GE Optima XR220amx Specifications

General IconGeneral
BrandGE
ModelOptima XR220amx
CategoryMedical Equipment
LanguageEnglish

Related product manuals