11 Commissioning Instructions
P253/EN M/C
11-11
7. If the required access level is not active the device will ask for a password to be entered so
that the setting change can be made.
8. If a P991/MMLG test block is installed, remove the P992/MMLB test plug and replace the
cover so that the protection is put into service.
9. Ensure that all event records, fault records, disturbance records, alarms and LEDs and
communications statistics have been reset.
Note: The Clear Maint function will clear all the Maintenance record memory.