GETINGE-LA CALHENE ISOTEST | User manual
NTA
3015/78 C
Approuvé informatiquement / Electronic signature
DEX | Page 20/
74
7.6. HANDLING
Before each sterilization cycle, Getinge-La Calhène recommends checking the integrity of
the isolator gloves. The method consists of:
conducting a test by raising the oxygen level to assess glove performance (GLT
testing device – operator manual NT 3020/1)
If the result of the test is "not correct", the glove must be replaced.
The procedure for replacing a glove without breach of containment is as follows:
Installation of gloves for an isolator under positive pressure
Pull the glove
(2) to be replaced inside out into the sleeve (1).
Remove the tightening ring (3).
Position the new glove (5) parallel to the cuff ring (4) aligning the axis of the thumb
with the seal of the sleeve.
Install the new glove (5) on the cuff ring (4) up from the bead (6) of the glove to be
replaced.
Place the tightening ring (3) around the glove behind the bead (6).
Position the bead (6) of the glove and the tightening ring (3) on the end of the cuff
ring groove
(4).
Remove the glove (2) from the sleeve (1).
Extract the glove (2).
1
2
3
4
5
6
1
2
3
4
6

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Getinge ISOTEST and is the answer not in the manual?

Getinge ISOTEST Specifications

General IconGeneral
BrandGetinge
ModelISOTEST
CategoryTest Equipment
LanguageEnglish