EasyManuals Logo

go-e Controller User Manual

go-e Controller
26 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #9 background imageLoading...
Page #9 background image
1616 1717
9. Installation (additional sensors)
The connection of a current transformer
is also sucient for measuring the cur-
rent of other 3-phase major consumers.
You can also use the current trans-
formers to measure the consumption
of individual circuits, such as lighting,
a boiler, air conditioner, sauna or heat
pump. When measuring these loads,
the arrow on the current transformer
should point in the direction of the
load.
The Controller now switches on and is
ready for operation after the system
has booted up. Most likely, the display
will still show wrong measured values,
we still have to assign the correct phase
and category to the sensors. Now you
have to carry out the initial congura-
tion. You can choose between these two
methods.
a) Commissioning/operation via the but-
tons and the display on the unit
b) Conguration via the app
5.
3.
When using WiFi repeaters, remem-
ber that they extend your home
network and do not create a new
network with a dierent IP address.
This works best with repeaters from the
same brand of your access point or WiFi
router.
If you have already installed go-e Char-
gers, they will be automatically recogni-
sed by the Controller after the congu-
ration has been completed. To do this,
the Controller has to be in the same net-
work as the Chargers. The Controller can
be connected to an unlimited number of
Chargers.
5
L1
3
You have installed all current transfor-
mers or do not want to use all sensors?
Have you completed the electrical con-
nection work? Then reconnect the pow-
er supply to the circuit.
4.
ON
4
You want to measure and visualise
your own PV production?
If you want to measure and visualise
your PV production, you must always
measure the current using a sensor on
one phase of your AC-PV inverter. For a
solar inverter, the arrow on the current
transformer should point from the in-
verter to the distribution board.
You have an AC battery storage sys-
tem that should be taken into ac-
count for the optimisation of the
power consumption?
Then use a current transformer to mea-
sure one phase of the battery storage.
This is only possible for AC battery sto-
rage systems. For an AC battery, the ar-
row on the current transformer should
point from the battery to the distributor.
Plug the jack plug of a current transfor-
mer into one of the inputs for current
measurement that are still free and mar-
ked "Sensor". You can assign them as you
wish. Clip the current transformer onto
one phase of the device or circuit whose
current ows you want to measure. With
3-phase devices that supply the same
power on all phases, measuring only
one phase is usually sucient. This is the
case, for example, with an AC inverter.
Again, please note that a current trans-
former may only be attached over one
phase, otherwise no measured values
can be recorded.
2.
After completing the basic installation,
you can use the remaining 3 to 5 current
transformers, depending on the type of
connection (single-phase or three-pha-
se), to measure the current ows of va-
rious devices or groups of consumers in
the building. This is suitable, for exam-
ple, for an AC PV inverter, an AC battery
storage system or large electrical consu-
mers such as boiler, air conditioning or
heat pump.
PV optimisation is also possible wit-
hout direct measurement of produc-
tion by the inverter.
PV System
Battery
A/C
Sauna
AC AC
Ensure that the circuit is de-energised by
observing the ve electrical safety rules.
1.
OFF
1
2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the go-e Controller and is the answer not in the manual?

go-e Controller Specifications

General IconGeneral
EnclosurePlastic
Communication InterfaceWiFi
ProtocolsModbus
Output Voltage230 V
Frequency50 Hz
ProtectionOvercurrent, Overvoltage