2  FLOW CHART OF INSTALLATION 
Design kicking-off
Material selection
Inspection of site installation position
Installation of indoor unit Installation of outdoor unit Installation of BU module
Installation of 
remote 
controller
Connection of 
power cables
Installation of drainage pipes
Thermal insulation of connection pipes and drainage pipes
Installation of refrigerant pipes 
Connection of 
transmission 
line
Connection of 
power cables
Connection of 
transmission 
line
Assign the 
address
Vacuum the system through 
the gas and liquid valves
Open the valves
Refrigerant charging
Test run
As-bulit drawing
Delivery of the operating instructions
Installation of 
piping adapter
Connection of 
power cables
Leakage test 
Commissioning of complete unit