Transporting And Lifting Instructions
Securing to truck or
trailer for transit
Always use the extension deck lock when the
machine is transported.
Fixed on the chassis in the transport plane
through fastening parts of machine.
Use a minimum of 4 chain or straps.
Use the chain or straps ample load capacity.
Turn the key switch to the off position and re-
move the key before transporting.
Inspect the entire machine for loose or unse-
cured items.
If the guardrails had be folded down, use the
straps to fix before transport.
Observe and obey:
√ Only qualified forklift operators should lift
the machine with a forklift.
√ Be sure the crane capacity, loading sur-
faces and straps or lines are sufficient to with-
stand the machine weight. See the serial label
for the machine weight.
Lifting the Machine with a Fork-
lift
Be sure the extension deck, controls and com-
ponent trays are secure. Remove all loose
items on the machine.
Fully lower the platform. The platform must re-
main lowered during all loading and transport
procedures.
Use the forklift pockets located on both sides
of the ladder.
Position the forklift forks in position with the
forklift pockets.
Drive forward to the full extent of the forks.
Raise the machine 0.15 m and then tilt the
forks back slightly to keep the machine secure.
Be sure the machine is level when lowering the
forks.
Lifting the machine from the