PRELIMINARYCHECK
COMMISSIONING
Check to ensure that the switch on the main power source has been ON for more than 12 hours,
in order to give the oil heater me to warm the compressor.
In three-phase unit check phase sequence connecon on terminal board.
Check the power supply voltage (±10% of the rated voltage).
Check that eld-supplied electrical components (main switches, breakers, wires, conduit
connectors and wire terminals) have been properly selected according to the electrical
specicaons given in this document, and check that the components comply with naonal and
local standards.
Do not touch any electrical components for more than three minutes aer turning OFF the main
switch.
Check the dip switch sengs of the indoor unit and the outdoor unit are connected as shown in
the corresponding chapter.
Check to ensure the electrical wiring of the indoor unit and the outdoor unit are connected as
shown in the chapter.
Check to ensure the external wiring is correctly xed. To avoid problems with vibraons, noises
and cut out wires with the plates.
8.2.3  Hydraulic circuit checking (space heang and DHW)
Check that the circuit has been properly ushed and lled with water and that the installaon
has been drained: the pressure of the heang circuit must be 1.8 bar.
Check for any leakage in water cycle. Pay special aenon to the water piping connecons.
Make sure the system’s internal water volume is correct.
Check that the hydraulic circuits valves are fully open.
Check to see that electrical heater is completely lled with water by operang pressure of safety
valve.
Check to see that addional water pumps (WP2 or/and WP3) are correctly connected to
terminal board.
! CAUTION
Operang the system with closed valves will damage the unit.
Check to see that air purge valve is open and that the hydrau lic circuit is air purged. The installer
is responsible of com pletely air purging the installaon.
Check that the water pump of the space heang circuit works within the pump operang range
and that the water ow is over the pump’s minimum. If the water ow is under 12 litres/minute
for 4.0-10.0HP (6 litres/minute for 2.0/2.5/3.0HP unit) (with ow switch tolerance), alarm will be
displayed on the unit.
Remember that water connecon must be accordance with local regulaons.
Water quality must comply with EU direcve 98/83 EC.
Electrical heater operaon when not completely lled with water will damage the heater.

Table of Contents

Other manuals for Hitachi YUTAKI S COMBI Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Hitachi YUTAKI S COMBI Series and is the answer not in the manual?

Hitachi YUTAKI S COMBI Series Specifications

General IconGeneral
TypeAir-to-Water Heat Pump
Energy Efficiency Class (Cooling)A++
RefrigerantR32
Operating Temperature Range (Heating)-20°C to 35°C
Energy Efficiency Class (Heating)A+++
Integrated DHW Tank190 liters
Dimensions (Indoor Unit)Varies by model
Dimensions (Outdoor Unit)Varies by model
Weight (Indoor Unit)Varies by model
Weight (Outdoor Unit)Varies by model
Operating Temperature Range (Cooling)+10°C to +46°C

Related product manuals