To connect a powder or solid detergent dispenser:
! Remove the rear panel.
! Drill a hole through the inner tank wall appropriate to the required
connection diameter (see fig.).
! Screw the dosing connection tightly to the tank wall.
! Connect the plug (B) of the wire harness with the dosage pump
(max. 100 VA).
Conductivity probe:
! Conductivity probe should be installed at the flat part of tank bot-
tom (see fig.).
! The hole size should be appropriate to the conductivity probe.
! Put panel(s) back into place.
! Switch on main switch at site or put the plug in.
! Dispenser and chemical sensor adjustment (see section 9.).
2. DISPENSER CONNECTION