Procedure
Step 1 Remove the AC terminal box and installing partition boards.
Figure 5-5 Removing the AC terminal box
Step 2 Connect the AC output power cable.
NO TE
Do not route a cable with a crimped OT terminal directly through the rubber liner.
Otherwise, the liner may be damaged.
Reserve sucient slack for the PE wire to ensure that the PE wire is the last cable
bearing the force when the AC output power cable is subject to a pulling force due to
force majeure. It is recommended that the stripping length of the PE cable be 15 mm
longer than that of other cables.
The cable colors shown in the gures are for reference only. Select an appropriate cable
according to the local standards.
Figure 5-6 Stripping an AC power cable (using a ve-core cable as an example)
SUN2000-(20KTL, 29.9KTL, 30KTL, 36KTL, 40KTL)-
M3
User Manual 5 Electrical Connections
Issue 18 (2024-03-10) Copyright © Huawei Technologies Co., Ltd. 45