Check Item Check Method Maintenance
Interval
Grounding
reliability
Check whether ground cables are
securely connected.
6 months after the
rst commissioning
and once every 6 to
12 months after that
Sealing Check whether all terminals and ports
are properly sealed.
Once 12 months
Vegetation
around the
inverter
Perform inspection and weeding as
required.
Clean the site promptly after
weeding.
Based on the local
wilting season
8.3 Alarm Reference
For details about alarms, see Inverter Alarm Reference.
SUN2000-(20KTL, 29.9KTL, 30KTL, 36KTL, 40KTL)-
M3
User Manual 8 Maintenance
Issue 18 (2024-03-10) Copyright © Huawei Technologies Co., Ltd. 82