Item Check Method Maintenance
Frequency
Electrical
connections
Check that cables are securely
connected.
If clamps are used for AC cable
connections, check that they are
secured with a torque of 35
N·m.
Check that cables are intact, in
particular, the parts touching
the metallic surface are not
scratched.
Check that the unused COM,
USB, and RESERVE ports are
covered by watertight caps.
The rst inspection is
six months after the
initial commissioning.
From then on, the
interval can be six or
twelve months.
Grounding
reliability
Check that ground cables are
securely connected.
The rst inspection is
six months after the
initial commissioning.
From then on, the
interval can be six or
twelve months.
8.2 Troubleshooting
Alarm severities are dened as follows:
Major: The inverter is faulty. As a result, the output power decreases or the
grid-tied power generation is stopped.
Minor: Some components are faulty without
aecting the grid-tied power
generation.
Warning: The inverter works properly. The output power decreases or some
authorization functions fail due to external factors.
SUN2000-(70KTL, 75KTL)-C1
User Manual 8 Maintenance
Issue 09 (2020-10-12) Copyright © Huawei Technologies Co., Ltd. 97

Table of Contents

Other manuals for Huawei SUN2000-75KTL-C1

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-75KTL-C1 and is the answer not in the manual?

Huawei SUN2000-75KTL-C1 Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-75KTL-C1
CategoryInverter
LanguageEnglish

Related product manuals