Maintenance log for XPR cutting systems
Daily tasks 12345678910111213141516171819202122232425262728293031
Do a test of the inlet pressures
Examine all of the air filters
Do a check of the coolant level and condition
Examine and lubricate O-rings
Examine the water tube and torch
Weekly tasks Week beginning: Week beginning: Week beginning: Week beginning: Week beginning:
Examine hoses, cables, and leads
Do tests for gas leaks
Do a check of the coolant flow
Monthly tasks (circle one) January February March April May June July August September October November December
Clean inside the plasma power supply Notes:
Examine the contactors
Examine the pilot arc relay
Examine the coolant system
Do the coolant flow test
Examine the gas line connections
Examine the hoses
Examine the cables
Examine the ground connections
Examine the table-to-workpiece connection
Every 6 months – Date completed: Replace the coolant and coolant filter, and clean and examine the pump screen