23
INSTALLATION
Esprit - Installation and Servicing
23
CONDENSATE PIPE TERMINATION CONFIGURATIONS . . . continued
3. INTERNAL CONNECTION TO SOIL AND VENT STACK
* Make connection to SVP using a solvent welded saddle
BOILER
External
wall
Ground Level
Termination
to Soak away
cla7774
minimum
500mm
BOILER
External
wall
Ground Level
Open end of pipe
direct into gulley
below grating but
above water level
DRAIN
cla7775
4. TERMINATION TO SOAK AWAY
5. TERMINATION TO DRAIN / GULLEY
BOILER
esp8882
INSTALLATION

Other manuals for IDEAL he30

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IDEAL he30 and is the answer not in the manual?

IDEAL he30 Specifications

General IconGeneral
Height700 mm
Output30 kW
Warranty2 years
Boiler typeCombi
MountingWall-mounted
Fuel TypeNatural Gas
ErP Water Heating EfficiencyA
TypeCombi Boiler
Efficiency89%