29
Transportation, Installation, Commissioning
LL1602.10043 - 04.08.2014
ABC
CHANGING THE LOCATION
Changing the location
For shipping as airfreight all charged pressure accumulators on
the machine have to be de-pressurised by a specialist.
Set main switch to OFF and secure against switching on.
Depressurize the hydraulic system by opening the pressure ac-
cumulator valves.
Provide the appropriate equipment for shipping the machine The equipment can be
ordered from INDEX giving the model and serial No. of the machine.
Replace the filler/breather with a screw plug.
See also "Important information before commissioning" manual.
The works described therein must be carried out in reverse
order.
Applicable only for machines with a chip conveyor
Disconnect the coolant supply hose at the joint above the coolant tank and dis-
connect the electricity supply to the coolant pump and to the chip conveyor drive
motor.
Pull out the chip conveyor and clean it.
Applicable only for machines with a bar feeder or a bar
loading magazine
Disconnect the two hydraulic lines P and T to the bar feeder or the bar loading
magazine.
With bar feeder: disconnect the plug connection of one electricity supply.
With bar loading magazine: disconnect the plug connections of three electricity sup-
plies.