Installation
Check that the maximum inlet pressure is not
higher than the design pressure of the regula-
tor.
Regulator should be lifted only with belts around
the body.
Arrange enough room for the serving of the
regulator.
Before installing the pressure regulator in the
piping, the following must be checked:
The upstream and downstream flanges must
be parallel so as to install the regulator without
undue stress.
The upstream piping must be cleaned from all
impurities (sand, welding slag, etc.)
The pressure regulator must not be visibly dam-
aged.
The inlet and outlet chambers of the pressure
regulator must be perfectly clean.
Make sure that the direction of gas flow corre-
sponds to the arrow on the pressure regulator
body.
Installation position
For ease of operation, we recommend perform-
ing installation with the valve body in horizontal
alignment, with actuator upwards.
Sensing line
The sensing line must be connected to a section
reasonably free from turbulences, preferably in
a straight section of the downstream piping (ap-
prox. 5D).
Connection: G
1
/
2
“/EO 12 (Regulator)
Connection: G
1
/
4
“/EO 6 (SSV)
Recommended pipe:
Ermeto-pipe EO-12 / -6, Steel, zinc protected
Breathing line
Breathing connection G
1
/
2
To realize fast load changes of the regulator,
the following cross sections of breathing line
are to observe:
Up to 3 m breathing line, min. size
DN 20
Longer than 3 m breathing line,
Size DN 25 or larger.
Start up- Instructions
To start-up the regulator after installation prop-
erly, proceed as follows:
(1) Check that the upstream- and downstream
valves are closed;
(2) If the regulator is fitted with the shut-off
valve, the shut-off valve must be closed;
(3)Open the upstream valve;
(4) Reset the shut-off valve slowly and check
that the downstream pressure is rising slowly on
the downstream side manometer. The down-
stream pressure should stop at the closing
pressure (see also page 29 to 32);
(5) Open the downstream valves slowly to con-
trol the even flow.
Regulator- and SSV-set point
The regulator is delivered according to the
specifications, specified in the purchase order.
If the adjusted outlet- / SSV shut off- pressure
is to be changed, proceed as follows:
Increasing the outlet- / shut off pressure:
The adjusting screw is to turn clockwise;
Decreasing the outlet- / shut off-pressure:
The adjusting screw is to turn anti-clockwise

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ITRON RR 16 and is the answer not in the manual?

ITRON RR 16 Specifications

General IconGeneral
BrandITRON
ModelRR 16
CategoryController
LanguageEnglish

Related product manuals