Commissioning protocol
AirModule –6 720 813 268(2014/10)
63
Power supply connection:
Is the phase order L1, L2, L3, N and PE in the heat pump and heat pump
module correct?
Yes | No
Has the power been connected according to the installation instructions? Yes | No
Heat pump and booster heater fuse, trip characteristics?
Manual mode:
Has a function test been performed of separate component assemblies
(circulation pump, mixing valve, 3-way valve, etc.)?
Yes | No
Notes:
Have the temperature values in the menu been checked and documented? Yes | No
T0
T1
TW1
TL5
TC0
TC1
________ °C
________ °C
________ °C
________ °C
________ °C
________ °C
Booster heater settings:
Start delay
Booster heater time delay
Block booster heater Yes | No
Immersion heater connected load settings
Booster heater max. temperature ________ °C
Electrical output (shows actual value)
Protective functions:
Block the heat pump during low outside temperature________ °C
Has the commissioning been performed correctly? Yes | No
Are there further actions required by the installer? Yes | No
Notes: