EasyManua.ls Logo

Johnson Controls York Smart Equipment SC-EQ - ProtoNode Wiring and Power Connections

Johnson Controls York Smart Equipment SC-EQ
52 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
JOHNSON CONTROLS
47
SECTION 6 - LON PROTONODE
FORM 450.50-N1
ISSUE DATE: 08/19/2019
6
PROTONODE
SC-EQ
WHITE
BLACK
RED
LD29258
FIGURE 56 - PROTONODE TO SC-EQ RS485 WIRING
4. For all OptiView panels (except on YS chillers),
complete the following steps:
1. Connect the power harness from the + PWR
and – PWR terminals on the JCI LON Proto-
Node to the locations as shown in Table 12.
The power harness, P/N 571-06580-401, is
included in the installation kit.
2. Connect the Frame GND on the ProtoNode
to a ground using the green/yellow wire, P/N
571-06580-403, included in the installation
kit.
3. Trim each of the cables to the required length.
4. Secure the power and communication cables
using wire ties and adhesive mounts provid-
ed in the installation kit.
TABLE 12 - POWER CONNECTIONS
CHILLER MODEL PWR+ PWR-
YK OptiView TB6-162 TB6-5
YZ OptiView TB7-162 TB7-5
YMC2 OptiView TB7-162 TB7-5
YD OptiView TB6-118 TB6-5
YKEP OptiView TB6-118 TB6-5
YT OptiView TB1-162 TB6-5
YR OptiView TB1-162 TB6-5
YST OptiView TB7-321 TB7-322
For YS OptiView panels, complete the following
steps:
1. Remove the power cable installed between
the micro board and the SC-EQ board.
2. Install the cable, P/N 571-08936-001, as fol-
lows:
connect P21 to J21 on the micro board
connect P9 to J9 on the SC-EQ board
connect the wire end to the ProtoNode
(red wire to PWR+, black wire to PWR-)
3. Trim the cable to the required length at the
ProtoNode end, if needed.
4. Install the Frame GND wire as described
previously in step 4.
LD29259
PWR+ PWR-
GND
FIGURE 57 - PROTONODE POWER WIRING

Table of Contents