14
EN
4 - INSTALLING THE PRODUCT
4.1 - Manual running
4.2 - Installing
3 - PRELIMINARY CHECKS
Before  the  installation  starts,  we  suggest  to  carry  out  following 
inspections and operations:
the gate framework must be strong and suitable;
the gate must not show too many sideways slide skids during the 
running;
the system of wheels/lower rail and roller/upper runner must work 
without too many frictions;
to avoid the gate derailment you must install the stop beats of the 
sliding, whether at the opening or closing, and a second upper 
roller/runner in full observance of the current law;
remove any manual lock in the beforehand gates;
take on the gate bottom the feed raceway of the feeding cables 
(Ø25-50mm) and of external connection (photocell, ash-light, key 
selector, etc...).
Insert the key and turn it 90° in anticlockwise direction.
Respecting  the  overall  size,  x  to  ground  the  base-plate  through 
4 sturdy screw-anchors (g.3) or drown it into the concrete (g.4).
N.B. The exact dimensions of the rack must be known to allow precise calculation of the counterplate position.
Pull the knob till it is perpendicular to the gearmotor.
Plan for one or more sheathing for the passage of the power lines.
Fig. 2
Fig. 3 Fig. 4
N.B. Take care to re-engage the gearmotor before starting it up. Engaging with the motor running may damage its internal components.