Keysight E4991B Impedance Analyzer 15
Installation
Installing Front Handles/Rack Mounting Flanges
1-
Installing Front Handles/Rack Mounting Flanges
The E4991B can be installed on a workbench or on a rack.
This section describes how to install the front handles (Option 1CN) used for
moving or transporting the instrument, and how to install the analyzer in an
eq
uipment rack as part of a measurement system (Option 1CM: without the
handles, Option 1CP: with the handles).
Figure 1-2 Installing front handle/rack mount kits
The handle kit (Option 1CN) is used for transporting and relocating of the
E
4
991B.
The rack-mount kit (Option 1CM) includes two flanges (locking side plates) for
mo
unting the E4991B on a rack (482.6 mm/19 inches) conforming to the EIA
Standard.
Option 1CP comes with both, the handle kit and rack-mount kit.