System Start-up Checklist
Date System Installed: / /
Installer and Address:
Phone Number: ( ) -
Start-Up Service Agency:
Phone Number: ( ) -
Comp. Discharge Pressure:
Suction Line Temp @ Comp.:
Discharge Line Temp @ Comp.:
Defrost Setting (4 day/45 min):
All electrical connections are tight:
Unit base properly supported:
Fans Running & No Vibration:
All guards, covers attached:
Refrigerant Sight Glass Clear:
Comp. Oil Level @ ½ Sight Glass:
Comp. Mounting Clips Removed:
Suction line insulated fully and properly supported:
Evaporator installed with nylon bolts with proper
airflow clearance:
Suction Line Temp @ Evap:
TXV Bulb Properly Mounted:
All guards, covers attached:
All electrical connections are tight:
Oil Trap at Base of Suction Riser:
Copper Drain Lines Sloped Min 1/2” ft:
Piping Supported Every 5’:
Copper drain line heater attached, working, and
insulated:
Copper Drain Line Trapped Outside Freezer
Space: