LAUNCH Electronic Two-post User’
s Manual
19
TLT235SBA
E
Model
The Base plate and four pieces
corrugated steel plate are connected by fasteners.(as
shown in Fig.7b)
Fig.7b
TLT240SCA Model
Base plate symmetric installation is as shown in 7c
1:
With total width (A) as the basis, draw two parallel
lines (#1 and #2) on the concrete slab, with the error
within 3mm. Determine the power side column
location on any chalk line, and mark the total width (B)
of the base plate. Mark the points 3 and 4. Starting
from point 3, draw one diagonal line (C) , forming a
triangle. In this way, the vertical lines can determine
the location of the two columns.
3420mm(134.6in)
2610mm(102.8in)
线
3
4
4
3
m
m
(
1
3
5
.
6
i
n
)
2820mm(111in)
70mm(2.8in)
4
0
0
m
m
(
1
5
.
7
i
n
)
1#
2#
3
4
C
A
B
Fig.7c
1
Base plate asymmetric installation is based on a total width
(A) shown in 7c
2,
draw two parallel lines (#1 and #2) on the
concrete slab, with the error within 3mm.Determine a point
B at any point on chalk line #1, based on point B, move
down 131mm, then move right 228mm to get point C.
Based on point B, draw #1’s vertical line M with a length of
A to get point D .Based on point C, draw line M’s parallel
line N with a length of L to get point E. With four points
B,C,D,E, each post’s position can be decided.
Diagonal 3443mm (135.6in)
(C) Diagtools; www.diagtools.eu; diagtools@diagtools.lv; Pernavas 43A, Riga, Latvia, LV-1009; +37129416069

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Launch TLT240SBA and is the answer not in the manual?

Launch TLT240SBA Specifications

General IconGeneral
BrandLaunch
ModelTLT240SBA
CategoryLifting Systems
LanguageEnglish

Related product manuals