Mechanical installation
Arrangement of the devices
4
44
EDK94ZPP0364 ZH/EN 2.0
A DC-bus connection with regenerative power supplymodulehasto beplanned
and dimensioned taking the technical data into account.
How to arrange the devices for operation in the DC-bus connection via the DC
busbars:
ƒ Arrange the devices in a row from left to right.
ƒ Install the supplying device on the left:
Regenerative power supply module with assigned mains filter (in a first
row),
Input module (in the following rows).
ƒ Install the multi drive axis controllers to the right from the highest to the
lowest power (recommendation).
ƒ For increasing the braking power also single drive axis controllers can be
integrated. For this purpose, these axis controllers have to be equipped
with the optional b usbar mounting set (E94AZJAxxx). In order to carry out
multi-supply applications, consult Lenze.