–28–
SUCTION SHUT-OFF VALVE INSULATION
The preformed suction shut-off valve insulation is
located in the plastic bag taped to the water curtain.
A. Verify valve and schrader caps are tightened to
specifications (see step 6).
B. Place insulation over schrader valve cap and left
side of valve. Position the tab between the
mounting bracket and rear panel.
C. Fold insulation and hold against right hand side of
valve while securing with electrical tape. Seal the
line set insulation to the shut-off valve insulation
with electrical tape.
PREFORMED
INSULATION
TIGHTEN VALVE CAPS
TO SPECIFICATIONS.
PLACE TAB BETWEEN
VALVE BODY AND PANEL.
FOLD INSULATION OVER
RIGHT SIDE OF VALVE
AND SECURE WITH
ELECTRICAL TAPE.