Page #31 background imageLoading...
Page #31 background image
DC8xD MK3 GENSET CONTROLLER USER MANUAL
30
date
function is disabled.
31
maintenance
expire
Warning
Alarm and stop
The action after the primary
maintenance expired.
32
User password
00000-65535(07623)
Change the password.
33
ATS in manual
mode
Disable/Enable
When it is set to enabled, when the
generator set meets the closing
conditions, it will be loaded
automatically.
2)Delay time setting
NO
Parameter
Range(default)
Notes
1
Start delay
0-65000s (5s)
The time during the genset starts after the
mains failure or remote signal is valid.
2
Preheat time
0-6500.0s (0.0s)
The time needed to be preheat before the
starter on power.
3
Cranking time
3.0-60.0s (8.0s)
The time when the starter is on power.
4
Crank rest time
3.0-60.0s (10.0s)
If crank failure, the waiting time before the
second test time.
5
Oil pressure delay
0-20.0s (0.0s)
When the crank condition contains oil
pressure, if the oil pressure is higher than the
preset value and continue for few seconds,
then it is regarded as crank success.
6
Safety delay
1.0-60.0s (8.0s)
Low oil pressure, high water temperature,
under speed, under frequency, under voltage,
charge failure are all invalid during this time
except for emergency stop and over speed.
7
Start idle time
0-3600.0s (5.0s)
Idle running time when crank successfully.
8
Longest RPM-up
time
0-3600.0s
(120.0s)
The longest speed-up time, during which time
the system will exit once speed increased
successfully.
9
Longest Warming-
up time
0-3600.0s (10.0s)
The time needed for loading.
10
Back to Mains time
0-3600.0s (10.0s)
To avoid the switch actions if the mains
unstable. If the remote start signal is invalid
(DC8XD MK3will check if the mains normal),
genset will not switch immediately, after the
delay time, it will transfer to mains. during the
delay, if the remote start signal is valid, then
genset will come into rated running.
11
Back to Gens time
0-3600.0s (5.0s)
There shall be loading delay from Mains to
Gens if the remote start signal valid or Mains
abnormal under Cooling time.
12
Cooling time
0-3600.0s (30.0s)
After unloading, the time of cooling down by
radiator before stop. during the delay, if the
remote start signal is valid, then genset will
come into rated running.
13
Stop idle time
0-3600.0s (5.0s)
Idle-speed running time.
14
E.T.S. hold time
0-600.0s (10.0s)
Stop solenoid on power time.
15
Fail to stop
5-180.0s (30.0s)
If the RPM is 0 during the stop failure time,
then the stop failure time is no needed.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Mebay DC8-D MK Series and is the answer not in the manual?

Mebay DC8-D MK Series Specifications

General IconGeneral
BrandMebay
ModelDC8-D MK Series
CategoryController
LanguageEnglish

Related product manuals