EasyManuals Logo

MEDENUS R 100 User Manual

MEDENUS R 100
52 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #15 background imageLoading...
Page #15 background image
15
© 11.2023
7.17
7.16
7.19
7.18
7.14
7.15
7.14
7.4 Initial Commissioning / Recommissioning
Initial commissioning of the system components shall be carried out by the operator. For commissioning, please refer to
the documents listed under item 1 “General Information” and the system operator's work instruction.
The devices delivered by MEDENUS Gas-Druckregeltechnik GmbH are factory-set to the operating data specified by the
customer. This data is listed on the Acceptance Test Certificate (ATC)* and the type plate.
Prior to commissioning of the system, a functional test must be performed on the gas pressure
regulator (GPR), if applicable, and the safety shut-off and safety relief valves.
Procedure (fig. 7.1)
Close the ball valve upstream of the valves and fittings (item 7.01).
Close the downstream shut-off devices (item 7.13) (ball valve, solenoid or pneumatic valve).
Depressurize the system (item 7.11).
Close the venting ball valve (item 7.11).
Slowly open ball valve upstream of the valves and fittings (item 7.01) (pressure increase approx. 0.5 bar/s).
If the inlet shut-off device is equipped with a bypass, the latter must be slowly opened for pressure
compensation as step 1. This is followed by slowly opening the inlet shut-off valve which will close the
bypass. The same is true of the outlet shut-off valve.
Check the inner leakage of the SSV (item 7.06) by reading the pressure gauge
installed downstream of the GPR (item 7.12).
Unscrew the sealing cap (item 7.15) of the safety shut-off valve (SSV).
Perform pressure compensation via the SSV by pulling at the pull knob (item
7.14) and allow the SSV to engage. On a GPR with bypass ball valve (item 7.28),
open the ball valve (item 7.28) while pulling the pull knob (item 7.14) until the
SSV engages to perform pressure compensation.
A closing pressure corresponding to the set value is established on the GPR.
Testing the response pressure of the SSV by slowly increasing or decreasing
the output pressure to response pressure.
It may be necessary to correct the setpoint values of the response pressures.
This is done by turning the SSV setpoint setting screws (items 7.17 / 7.19) to
the right (pressure increase) or left (pressure decrease) in order to increase/
decrease the setpoint value.
The inner setting screw (item 7.17) sets the underpressure shut-off
level (lower trigger level) and the outer setting screw (item 7.19) sets
the upper trigger level.
Perform pressure compensation via the SSV again by pulling the pull knob
(item 7.14) and allowing the SSV to engage.
*) Acceptance Test Certificate (ATC) available optionally
Note
Note
Note
Fig. 7.3
Fig. 7.4

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the MEDENUS R 100 and is the answer not in the manual?

MEDENUS R 100 Specifications

General IconGeneral
BrandMEDENUS
ModelR 100
CategoryController
LanguageEnglish

Related product manuals