GB
CS 300 Gate Controls / rev. 04.06 – 5
5. Initial Operation
5.1 General5.1 General
Warning! Warning!
To guarantee that the equipment
functions properly, the following points
must be ensured:
- The gate or door is installed and ope
rational.
- The MFZ drive motor is installed and
ready for operation.
- The command and safety devices are
installed and ready for operation.
- The control housing with the CS 300
control is installed.
Information:Information:
For the installation of the gate/door,
the MFZ drive motor and the command
and safety devices, the relevant
manufacturer’s instructions are to
be adhered to.
5.2 Mains connection5.2 Mains connection
Danger! Danger!
To guarantee that the controls function
properly, the following points must be
ensured:
- The mains voltage must correspond
to the voltage stated on the type
plate.
- For a three-phase current, a
clockwise rotating fi eld is required.
- For a permanent connection, an
all-pole main switch must be used.
- For a three-phase connection, only
3-way automatic circuit breakers
(10A) may be used.
Detailed circuit diagram for mains connection and
motor
UVWB1B2
L1 L2 L3 N
PE
PE
PE
13 5 13 5
24 6 24 6
X2
X1
X11
T1
K2
K1
M
M1
Key:
K1: protection, CLOSE
K2: protection, OPEN
M1: motor
T1: transformer
X1: terminal block for mains connection
X2: terminal block for motor
X11: sockets for digital end position system with
safety circuit (STOP CIRCUIT)
Connection:
Connect the digital end-position system to the Connect the digital end-position system to the
control.control.
Connect the control to the mains.Connect the control to the mains.
Connect the control to the motor.Connect the control to the motor.
☞
☞
☞
GB