7 - 64
7.10 Job Setting
7.10.2 Setting items in Trigger conditions
7
MES INTERFACE FUNCTION CONFIGURATION TOOL
(2) Trigger 1, Trigger 2
Select items for [Trigger 1] and [Trigger 2], referring to (3) and subsequent
descriptions.
: Selectable,
×: Not selectable
When using 'Value monitoring startup' or 'Handshake operation' for a trigger
condition, check that 'Information linkage status (X5)' is in execution (ON), and
create a program so that the trigger condition is satisfied.
Section 2.6.5 (1) Startup time
(3) Disable
(a) When [Disable] is selected for [Trigger 1] or [Trigger 2]
Another trigger is regarded as a trigger condition.
(b) When [Disable] is selected for both [Trigger 1] and [Trigger 2]
The job is not activated by trigger conditions.
When [Disable] is selected, the job can be activated by an "instruction of job
execution" of the XML processing function.
Section 6.2 XML Processing Function
Table 7.49 Selection items for [Trigger 1] and [Trigger 2]
Item Description Trigger 1 Trigger 2
Disable
No trigger conditions
(3) Disable in this section
Time specification startup
When the specified date, time and day of the week match
the actual date, time and day of the week, the condition
changes from false to true, resulting in job startup.
(4) Time specification startup in this section
Specified time period
startup
The condition is alternated between true and false in the
specified cycles (unit: seconds), and when it changes from
false to true, the job is activated.
(5) Specified time period startup in this section
Value monitoring startup
The actual tag component value is compared with the
condition value (tag component value or constant value) at
every sampling times, and the job is activated when the
condition changes from false to true.
(6) Value monitoring startup in this section
At module startup
The job is activated only once when the MES interface
module is started up.
(7) At module startup in this section
Handshake operation
The job is activated when [Handshake startup] of the
programmable controller CPU turns ON.
Upon completion of the job execution, [Completion
notification] of the programmable controller CPU turns ON.
(8) Handshake operation in this section
×