Setting voltage point back
to battery mode when
selecting “SBU” (SBU
priority) or “SUB” (Solar
first) in program 01
5KW model: The setting range is from 48.0V to 64.0V and
increment of each click is 1.0V.
Solar energy priority:
To configure solar energy
priority for battery and load
SbL: Solar energy for
battery first
UCB: Allow utility to charge
battery (Default)
Solar energy charges battery first
and allow the utility to charge
battery.
SbL: Solar energy for
battery first
UdC: Disallow utility to
charge battery
Solar energy charge battery first
and disallow the utility to charge
battery.
SLb: Solar energy for load
first
UCb: Allow utility to charge
battery
Solar energy provides power to the
load first and also allow the utility
to charge battery.
SLb: Solar energy for load
first
UdC: Disallow utility to
charge battery
Solar energy provides power to the
load first and disallow the utility to
charge battery.