16 Part Number 9294699 12/16/15
Installation Section 2
Tune-Up Reminder
10. The Tune-Up reminder screen will appear during initial
installation, press the green check to continue.
11. The red wrench at the top of the screen and reminder
will periodically popup until the installation date is set
in the Managers Menu.
NOTE: This will be done once Start-Up and Cleaning have
been completed.
12. Press the Back Arrow in the lower left corner to access
the Main Menu.
13. Select the Cleaning Icon.
14. Select Zone 2, Clean and sanitize the Blend-In-Cup
machine by following the on screen instructions.
NOTE: See “Weekly Cleaning - Zone 2” on page 43. By
doing so, the following will have been completed:
A. All beverage lines, ice bin, dispense area, and blender
chambers, cleaned and sanitized.
B. Water run through the drain to verify it is draining properly.
C. Verify all regulators are set correctly during
cleaning.
NOTE: During the cleaning process is an ideal time to verify
pressure regulator settings during flowing conditions. See
“Regulator Settings & Location” on page 14
D. Ice bin manually filled with ice. See “Manual Fill Ice” on
page 34 .
E. Product bags retrieved from walk-in cooler, installed into
the product bins and placed into their proper location in
the cabinet. See “Procedure to Install a Product Bag” on
page 32 & “Assigning Flavors” on page 28.
F. All product lines primed and ready for use.
Label
15. Add labels to product bins, put labels in correct place.
16. Add labels anywhere else on the unit required.
Software
17. Load recipes. See “Loading Recipes” on page 34.
18. Verify correct drinks and flavors are available.
Drink Selection Screen
(Drink choices will vary depending on loaded recipe file)