Inspection of the installation
Current regulations require the heating installation to be inspected before it is commissioned. The inspection must be
carried out by a suitably qualified person. Fill in the page for information about installation data in the User manual.
DateSignatureNotesDescription
Heating medium (page 23)
System flushed
System vented
Particle filter
Shut-off and drain valve
Charge flow set
Electricity (page 25)
Fuses property
Safety breaker
Earth circuit-breaker
Heating cable type/effect
Fuse size, heating cable (F3)
Communication cable connected
F2050 addressed (onlywhen cascade connec-
tion)
Connections
Main voltage
Phase voltage
When installing F2050-6, check that the
software version of the indoor module/control
module is at least v8320.
Miscellaneous
Warranty
Benchmark checklist
NIBE F2050Chapter 1 | Important information6