79 
12.5.2  Install the Outdoor Unit 
  After selecting the best location, start installation to Indoor/Outdoor Unit Installation Diagram. 
1  Fix the unit on concrete or rigid frame firmly and horizontally by bolt nut (ø10 mm). 
Make sure unit install in balance level to ensure that water flow out from unit drainage hole. 
2  When installing at roof, please consider strong wind and earthquake. 
Please fasten the installation stand firmly with bolt, screws or nails. 
 
 
 
 
 
Model  A  B  C  D 
TZ20*** 
570 mm  105 mm  18.5 mm 320 mm
TZ25***, RZ25*** 
TZ35***, RZ35*** 
TZ42*** 
TZ50***, RZ50*** 
540 mm  160 mm  18.5 mm 330 mm
TZ60*** 
TZ71***  613 mm  131 mm  24 mm  360.5 mm
 
12.5.3  Connect the Piping 
12.5.3.1 Connecting the Piping to Indoor 
For connection joint location at outside building 
Please make flare after inserting flare nut (locate at 
joint portion of tube assembly) onto the copper pipe. 
(In case of using long piping) 
Connect the piping 
  Align the center of piping and sufficiently tighten 
the flare nut with fingers. 
  Further tighten the flare nut with torque wrench in 
specified torque as stated in the table. 
 
 
For connection joint location at inside building 
  Refer to indoor installation instruction. 
 
 
 
 
 
 
 
 
 
 
 
 
12.5.3.2 Connecting the Piping to Outdoor 
Decide piping length and then cut by using pipe cutter. 
Remove burrs from cut edge. 
Make flare after inserting the flare nut (locate at valve) 
onto the copper pipe. Align center of piping to valve 
and then tighten with torque wrench to the specified 
torque as stated in the table. 
 
 
 
 
 
Do not overtighten, overtightening may cause gas leakage. 
 
 
Piping size  Torque 
6.35 mm (1/4")  [18 N•m (1.8 kgf•m)] 
9.52 mm (3/8")  [42 N•m (4.3 kgf•m)] 
12.7 mm (1/2")  [55 N•m (5.6 kgf•m)] 
15.88 mm (5/8")  [65 N•m (6.6 kgf•m)] 
19.05 mm (3/4")  [100 N•m (10.2 kgf•m)] 
 
 
 
 
 
 
 
 
 
 
 
AB
C
D
Torque 
wrench
Spanner or 
Wrench